10 U.S.C. § 2435
Section 2435 · Baseline description
Current version, with additions and removals from the December 28, 2001 version.
(d) Original Baseline Estimate.—(1) In this chapter, the term "original Baseline Estimate", with respect to a major defense acquisition program or any designated major subprogram under the program, means the baseline description established with respect to the program or subprogram under subsection (a) prepared before the program or subprogram enters system development and demonstration, or at program or subprogram initiation, whichever occurs later, without adjustment or revision (except as provided in paragraph (2)).
(2) An adjustment or revision of the original baseline description of a major defense acquisition program or any designated major subprogram under the program may be treated as the original Baseline Estimate for the program or subprogram for purposes of this chapter only if the percentage increase in the program acquisition unit cost or procurement unit cost under such adjustment or revision exceeds the critical cost growth threshold for the program or subprogram under section 2433 of this title, as determined by the Secretary of the military department concerned under subsection (d) of such section.
(3) In the event of an adjustment or revision of the original baseline description of a major defense acquisition program or any designated major subprogram under the program, the Secretary of Defense shall include in the next Selected Acquisition Report to be submitted under section 2432 of this title after such adjustment or revision a notification to the congressional defense committees of such adjustment or revision, together with the reasons for such adjustment or revision.
(1) The content of baseline descriptions under this section.
(3) Procedures for review of such deviation reports within the Department of Defense.
(4) Procedures for submission to, and approval by, the Secretary of Defense of revised baseline descriptions.