Public-domain · open source
OpenJurist

current Baseline Estimate

Defined in 1 dictionary — U.S. Code

United States Code

50 U.S.C. § 415a-7 — in this section

(A) The term “current Baseline Estimate” means the projected total acquisition cost of a major system that is—

(i) approved by the Director, or a designee of the Director, at Milestone B or an equivalent acquisition decision for the development, procurement, and construction of such system;

(ii) approved by the Director at the time such system is restructured pursuant to section 415a–8(c) of this title; or

(iii) the 2010 adjusted total acquisition cost determined pursuant to subsection (h).

(B) A current Baseline Estimate may be in the form of an independent cost estimate.

50 U.S.C. § 415a-8 — in this section

In this section, the terms “cost estimate”, “critical cost growth threshold”, “current Baseline Estimate”, “major system”, and “total acquisition cost” have the meaning given those terms in section 415a–7(a) of this title.

50 U.S.C. § 3101 — in this section (2 versions over time)

The term “current Baseline Estimate” means the projected total acquisition cost of a major system that is—

(i) approved by the Director, or a designee of the Director, at Milestone B or an equivalent acquisition decision for the development, procurement, and construction of such system;

(ii) approved by the Director at the time such system is restructured pursuant to section 3102(c) of this title; or

(iii) the 2010 adjusted total acquisition cost determined pursuant to subsection (h).

50 U.S.C. § 3102 — in this section (2 versions over time)

In this section, the terms “cost estimate”, “critical cost growth threshold”, “current Baseline Estimate”, “major system”, and “total acquisition cost” have the meaning given those terms in section 3101(a) of this title.

Show all 4 definitions and how they changed over time