Cal. Gov. Code § 4216.2

Regional Notification Center System

Redline — January 1, 2011 → current.View current text →
Current — January 1, 2025
As of January 1, 2011
(a) (1) Except in an emergency, any person planning to conduct any excavation shall contact the appropriate regional notification center, at least two working days, but not more than 14 calendar days, prior to commencing that excavation, if the excavation will be conducted in an area that is known, or reasonably should be known, to contain subsurface installations other than the underground facilities owned or operated by the excavator and, if practical, the excavator shall delineate with white paint or other suitable markings the area to be excavated.
(a) Before notifying the appropriate regional notification center, an excavator planning to conduct an excavation shall delineate the area to be excavated. If the area is not delineated, an operator may, at the operator’s discretion, choose not to locate and field mark until the area to be excavated has been delineated.
(b) Except in an emergency, an excavator planning to conduct an excavation shall notify the appropriate regional notification center of the excavator’s intent to excavate at least two working days, and not more than 14 calendar days, before beginning that excavation. The date of the notification shall not count as part of the two-working-day notice. If an excavator gives less notice than the legal excavation start date and time and the excavation is not an emergency, the regional notification center will take the information and provide a ticket, but an operator has until the legal excavation start date and time to fulfill their obligations under subparagraph (A) of paragraph (1) of subdivision (a) of Section 4216.3. However, an excavator and an operator may mutually agree to a different notice and start date. The contact information for operators notified shall be available to the excavator.
(2) When the excavation is proposed within 10 feet of a high priority subsurface installation, the operator of the high priority subsurface installation shall notify the excavator of the existence of the high priority subsurface installation prior to the legal excavation start date and time, as such date and time are authorized pursuant to paragraph (1) of subdivision (a) of Section 4216.2. The excavator and operator or its representative shall conduct an onsite meeting at a mutually-agreed-on time to determine actions or activities required to verify the location of the high priority subsurface installations prior to start time.
(c) When the excavation is proposed within 10 feet of a high priority subsurface installation, the operator of the high priority subsurface installation shall notify the excavator of the existence of the high priority subsurface installation to set up an onsite meeting prior to the legal excavation start date and time or at a mutually agreed upon time to determine actions or activities required to verify the location and prevent damage to the high priority subsurface installation. As part of the meeting, the excavator shall discuss with the operator the method and tools that will be used during the excavation and the information the operator will provide to assist in verifying the location of the subsurface installation. The excavator shall not begin excavating until after the completion of the onsite meeting.
(b) Except in an emergency, every excavator covered by Section 4216.8 planning to conduct an excavation on private property may contact the appropriate regional notification center if the private property is known, or reasonably should be known, to contain a subsurface installation other than the underground facility owned or operated by the excavator and, if practical, the excavator shall delineate with white paint or other suitable markings the area to be excavated.
(d) Except in an emergency, every excavator covered by Section 4216.8 planning to conduct an excavation on private property that does not require an excavation permit may contact the appropriate regional notification center if the private property is known, or reasonably should be known, to contain a subsurface installation other than the underground facility owned or operated by the excavator. Before notifying the appropriate regional notification center, an excavator shall delineate the area to be excavated. Any temporary marking placed at the planned excavation location shall be clearly seen, functional, and considerate to surface aesthetics and the local community. An excavator shall check if any local ordinances apply to the placement of temporary markings.
(c) The regional notification center shall provide an inquiry identification number to the person who contacts the center pursuant to this section and shall notify any member, if known, who has a subsurface installation in the area of the proposed excavation. An inquiry identification number may be validated for more than 28 days when mutually agreed between the excavator and any member operator so notified that has a subsurface installation in the area of the proposed excavation; and, it may be revalidated by notification to the regional notification center by the excavator prior to the time of its expiration.
(e) The regional notification center shall provide a ticket to the person who contacts the center pursuant to this section and shall notify any member, if known, who has a subsurface installation in the area of the proposed excavation. A ticket shall be valid for 28 days from the date of issuance. If work continues beyond 28 days, the excavator shall renew the ticket either by accessing the center’s internet website or by calling “811” by the end of the 28th day.
(d) A record of all notifications by excavators and operators to the regional notification center shall be maintained for a period of not less than three years. The record shall be available for inspection by the excavator and any member, or their representative, during normal working hours and according to guidelines for inspection as may be established by the regional notification centers.
(f) A record of all notifications by an excavator or operator to the regional notification center shall be maintained for a period of not less than three years. The record shall be available for inspection by the excavator and any member, or their representative, during normal working hours and according to guidelines for inspection as may be established by the regional notification centers. A regional notification center shall provide notification records to the board quarterly and shall provide notifications of damage to the board within five business days of receipt at the regional notification center.
(e) As used in this section, the delineation is practical when any of the following conditions exist:
(1) When delineating a prospective excavation site with white paint could not be misleading to those persons using affected streets and highways.
(2) When the delineation could not be misinterpreted as a traffic or pedestrian control.
(3) Where an excavator can determine the exact location of an excavation prior to the time an area has been field marked pursuant to Section 4216.3.
(4) Where delineation could not be construed as duplicative.
(f) Where an excavator makes a determination that it is not practical to delineate the area to be excavated, the excavator shall contact the regional notification center to advise the operators that the excavator shall identify the area to be excavated in another manner sufficient to enable the operator to determine the area of the excavation to be field marked pursuant to Section 4216.3.
(g) (1) Unless an emergency exists, an excavator shall not begin excavation until all operators of subsurface installations that are listed on the ticket have fulfilled their obligations under subparagraph (A) of paragraph (1) of subdivision (a) of Section 4216.3 and until the completion of any onsite meeting, if required by subdivision (c).
(2) The excavator may begin excavation before the legal excavation start date and time if all of the conditions in paragraph (1) have been satisfied.
(h) If a site requires special access, an excavator shall request an operator to contact the excavator regarding that special access or give special instructions on the location request.
(i) If a ticket obtained by an excavator expires but work is ongoing, the excavator shall immediately cease excavation, contact the regional notification center, and get a new ticket pursuant to subdivision (b), and may not resume excavation until the conditions in subdivision (g) have been satisfied.

Official source: California Legislative Information. Reproduced from public-domain California statutes; confirm against the official source for the current text. Not legal advice.