Cal. Pub. Util. Code § 911

Reports to the Legislature

Redline — January 1, 2013 → current.View current text →
Current — January 1, 2015
As of January 1, 2013
(a) Notwithstanding subdivision (g) of Section 454.5 and Section 583, no later than May 1 of each year, the commission shall release to the Legislature the costs of all electricity procurement contracts for eligible renewable energy resources, including unbundled renewable energy credits, and all costs for utility-owned generation approved by the commission. The first report shall include all costs commencing January 1, 2003. Subsequent reports shall include only costs for the preceding calendar year.
(1) For power purchase contracts, the commission shall release costs in an aggregated form categorized according to the year the procurement transaction was approved by the commission, the eligible renewable energy resource type, including bundled renewable energy credits, the average executed contract price, and average actual recorded costs for each kilowatthour of production. Within each renewable energy resource type, the commission shall provide aggregated costs for different project size thresholds.
(2) For each utility-owned renewable generation project, the commission shall release the costs forecast by the electrical corporation at the time of initial approval and the actual recorded costs for each kilowatthour of production during the preceding calendar year.
(b) This section does not require the release of the terms of any individual electricity procurement contracts for eligible renewable energy resources, including unbundled renewable energy credits, approved by the commission. The commission shall aggregate data to the extent required to ensure protection of the confidentiality of individual contract costs even if this aggregation requires grouping contracts of different energy resource type. The commission shall not be required to release the data in any year when there are fewer than three contracts approved.
(c) The commission may combine the information required by this section with the report prepared pursuant to Section 910, as added by Chapter 1 of the First Extraordinary Session of the Statutes of 2011.
(a) Beginning February 1, 2016, the commission shall annually publish a report that includes all investigations into gas or electric service safety incidents reported, pursuant to commission requirements, by any gas corporation or electrical corporation. The report shall succinctly describe each safety investigation concluded during the prior calendar year and each investigation that remains open. The categories within the description shall include the month of the safety incident, the reason for the investigation, the facility type involved, and the owner of the facility.
(b) The commission shall include in its report required pursuant to Section 910, a summary of the staff safety investigations concluded during the prior calendar year and the staff safety investigations that remain open for any gas corporation or electrical corporation, with a link to the Internet Web site with the report that contains the information required pursuant to subdivision (a).

Official source: California Legislative Information. Reproduced from public-domain California statutes; confirm against the official source for the current text. Not legal advice.