The Legislature finds that it is beneficial to have an alternative method to resolve construction disputes that would reduce the need for litigation as well as protect the rights of property owners. An effective alternative dispute resolution mechanism in certain construction defect matters should involve the claimant filing a notice of claim with the contractor, subcontractor, supplier, or design professional that the claimant asserts is responsible for the defect, and should provide the contractor, subcontractor, supplier, or design professional with an opportunity to resolve the claim without resort to further legal process.
Fla. Stat. § 558.001
Legislative findings and declaration
Showing this section's text as in effect on January 1, 2011 (in force January 1, 2011 – January 1, 2015). View current text →
Official source: Online Sunshine (Florida Legislature). Reproduced from public-domain Florida statutes; confirm against the official source for the current text. Not legal advice.