Iowa Code § 459A.207
Construction certification
Redline — January 1, 2012 → current.View current text →
Current — January 1, 2017
As of January 1, 2012
1. The owner of an open feedlot operation who is issued a construction permit for a settled open feedlot effluent basin as provided in section 459A.205 after July 1, 2005, shall submit to the department a construction certification from a licensed professional engineer certifying all of the following:
1. The owner of an open feedlot operation who is issued a construction permit for a settled open feedlot effluent basin or the owner of an animal truck wash facility who is issued a construction permit for an animal truck wash effluent structure as provided in section 459A.205 shall submit to the department a construction certification from a professional engineer certifying all of the following:
a. The basin was constructed in accordance with the design plans submitted to the department as part of an application for a construction permit pursuant to section 459A.205. If the actual construction deviates from the approved design plans, the construction certification shall identify all changes and certify that the changes were consistent with all applicable standards of this section.
a. The basin or structure was constructed in accordance with the design plans submitted to the department as part of an application for a construction permit pursuant to section 459A.205. If the actual construction deviates from the approved design plans, the construction certification shall identify all changes and certify that the changes were consistent with all applicable standards of this section.
b. The basin was inspected by the licensed professional engineer after completion of construction and before commencement of operation.
b. The basin or structure was inspected by the professional engineer after completion of construction and before commencement of operation.
2. A written record of an investigation for drainage tile lines, including the findings of the investigation and actions taken to comply with subchapter III, shall be submitted as part of the construction certification.
2. A written record of an investigation for drainage tile lines, including the findings of the investigation and actions taken to comply with subchapter III, shall be submitted as part of the construction certification.
Referred to in
Official source: Iowa Legislature. Reproduced from public-domain Iowa statutes; confirm against the official source for the current text. Not legal advice.