Iowa Code § 572.10

Perfecting lien after lapse of ninety days

Redline — January 1, 2017 → current.View current text →
Current — January 1, 2020
As of January 1, 2017
A general contractor or a subcontractor may perfect a mechanic’s lien pursuant to section 572.8 beyond ninety days after the date on which the last of the material was furnished or the last of the labor was performed by posting a lien to the mechanics’ notice and lien registry internet site and giving written notice thereof to the owner. Such notice may be served by any person in the manner original notices are required to be served. If the party to be served is out of the county wherein the property is situated, a return of that fact by the person charged with making such service shall constitute sufficient service from and after the time it was posted to the mechanics’ notice and lien registry internet site.
A general contractor or a subcontractor may perfect a mechanic’s lien pursuant to section 572.8 beyond ninety days after the date on which the last of the material was furnished or the last of the labor was performed by posting a lien to the mechanics’ notice and lien registry internet site and giving written notice thereof to the owner. Such notice may be served by any person in the manner original notices are required to be served. If the party to be served is out of the county wherein the property is situated, a return of that fact by the person charged with making such service shall constitute sufficient service from and after the time it was posted to the mechanics’ notice and lien registry internet site.
87 Acts, ch 79, §2; 2007 Acts, ch 83, §6; 2012 Acts, ch 1105, §6, 27, 28; 2012 Acts, ch 1138, §13, 40, 43; 2013 Acts, ch 90, §257
87 Acts, ch 79, §2; 2007 Acts, ch 83, §6; 2012 Acts, ch 1105, §6, 27, 28; 2012 Acts, ch 1138, §13, 40, 43; 2013 Acts, ch 90, §257
Service of notice, R.C.P. 1.302 – 1.315
Service of notice,
2012 amendments to section take effect January 1, 2013; mechanics’ liens filed prior to that date shall remain with the clerk of district court of the county in which the building, land, or improvement charged with the lien is situated;
Notice provisions contained in 2012 Acts, ch 1105, relating to residential construction apply only to material furnished or labor performed after January 1, 2013;