Iowa Code § 572.14

Liability to subcontractor after payment to general contractor or owner-builder

Redline — January 1, 2012 → current.View current text →
Current — January 1, 2020
As of January 1, 2012
1. Except as provided in subsection 2, payment to the original contractor by the owner of any part or all of the contract price of the building or improvement within ninety days after the date on which the last of the materials was furnished or the last of the labor was performed by a subcontractor, does not relieve the owner from liability to the subcontractor for the full value of any material furnished or labor performed upon the building, land, or improvement if the subcontractor files a lien within ninety days after the date on which the last of the materials was furnished or the last of the labor was performed.
Except as provided in section 572.13B, payment to the general contractor or owner-builder of any part or all of the contract price of the building or improvement within ninety days after the date on which the last of the materials was furnished or the last of the labor was performed by a subcontractor, does not relieve the owner from liability to the subcontractor for the full value of any material furnished or labor performed upon the building, land, or improvement if the subcontractor posts a lien within ninety days after the date on which the last of the materials was furnished or the last of the labor was performed.
2. In the case of an owner-occupied dwelling, a mechanic’s lien perfected under this chapter is enforceable only to the extent of the balance due the principal contractor by the owner-occupant prior to the owner-occupant being served with the notice specified in subsection 3. This notice may be served by delivering it to the owner or the owner’s spouse personally, or by mailing it to the owner by certified mail with restricted delivery and return receipt to the person mailing the notice, or by personal service as provided in the rules of civil procedure.
3. The written notice required for purposes of subsection 2 shall contain the name of the owner, the address of the property charged with the lien, the name, address and telephone number of the lien claimant, and the following statement:
The person named in this notice is providing labor or materials or both in connection with improvements to your residence or real property. Chapter 572 of the Code of Iowa may permit the enforcement of a lien against this property to secure payment for labor and materials supplied. You are not required to pay more to the person claiming the lien than the amount of money due from you to the person with whom you contracted to perform the improvements. You should not make further payments to your contractor until the contractor presents you with a waiver of the lien claimed by the person named in this notice. If you have any questions regarding this notice you should call the person named in this notice at the phone number listed in this notice or contact an attorney. You should obtain answers to your questions before you make any payments to the contractor.
87 Acts, ch 79, §6; 98 Acts, ch 1142, §3; 2007 Acts, ch 83, §10
87 Acts, ch 79, §6; 98 Acts, ch 1142, §3; 2007 Acts, ch 83, §10; 2012 Acts, ch 1105, §11, 27, 28; 2012 Acts, ch 1138, §13
Referred to in

Official source: Iowa Legislature. Reproduced from public-domain Iowa statutes; confirm against the official source for the current text. Not legal advice.