Ind. Code § 13-18-23-1

Deadline for department action; requirements; waiver

Redline — January 1, 2018 → current.View current text →
Current — January 1, 2023
As of January 1, 2018
Sec. 1. (a) The department shall:
Sec. 1. (a) The department shall do the following:
(1) make a final determination on an application for a certification under Section 401 of the Clean Water Act not later than one hundred twenty (120) days after its receipt of a complete application; and
(1) Make a final determination on an application for a certification under Section 401 of the Clean Water Act not later than ninety (90) days after its receipt of a complete application if the applicant meets the condition set forth in subsection (b).
(2) include in its notice of the final determination to the applicant a statement of reasons for the final determination.
(2) Include in its notice of the final determination to the applicant a statement of reasons for the final determination.
(b) At least thirty (30) days before submitting an application under this section, an applicant must contact the department to request a pre-coordination meeting.
(b) A failure by the department to act within the period specified in subsection (a)(1) constitutes a waiver of the certification.
(c) A failure by the department to make a final determination not later than ninety (90) days after receiving a complete application, if required under subsection (a)(1), constitutes a waiver of the certification.