Public-domain · open source
OpenJurist

Ind. Code § 36-1-29-16

Application for seawall or revetment permit other than emergency permit; time frame for approval or denial by local authority

As added by P.L.164-2020, SEC.64

Sec. 16. (a) This section applies to an application for a seawall or revetment permit that is not an emergency permit.

(b) Not later than thirty (30) business days after a person submits a completed application and meets all required conditions for a seawall or revetment permit, a local authority shall:

(1) approve; or

(2) deny;

the person's application for the permit.

(c) If a local authority does not approve or deny the seawall or revetment permit within thirty (30) business days, the permit is automatically approved and considered issued to the person.