Ind. Code § 8-1-40-12

Amendment of commission's net metering rules and electricity suppliers' net metering tariffs; increase to aggregate net metering facility nameplate capacity; reservation of capacity for residential customers and organic waste biomass facilities

Redline — January 1, 2018 → current.View current text →
Current — January 1, 2025
As of January 1, 2018
Sec. 12. (a) Before January 1, 2018, the commission shall amend 170 IAC 4-4.2-4, and an electricity supplier shall amend the electricity supplier's net metering tariff, to do the following:
Sec. 12. Before January 1, 2018, the commission shall amend 170 IAC 4-4.2-4, and an electricity supplier shall amend the electricity supplier's net metering tariff, to do the following:
(1) Increase the allowed limit on the aggregate amount of net metering facility nameplate capacity under the net metering tariff to one and one-half percent (1.5%) of the most recent summer peak load of the electricity supplier.
(1) Increase the allowed limit on the aggregate amount of net metering facility nameplate capacity under the net metering tariff to one and one-half percent (1.5%) of the most recent summer peak load of the electricity supplier.
(2) Modify the required reservation of capacity under the limit described in subdivision (1) to require the reservation of: (A) forty percent (40%) of the capacity for participation by residential customers; and (B) fifteen percent (15%) of the capacity for participation by customers that install a net metering facility that uses a renewable energy resource described in IC 8-1-37-4(a)(5). (b) In amending 170 IAC 4-4.2-4, as required by subsection (a), the commission may adopt emergency rules in the manner provided by IC 4-22-2-37.1. Notwithstanding IC 4-22-2-37.1(g), an emergency rule adopted by the commission under this section and in the manner provided by IC 4-22-2-37.1 expires on the date on which a rule that supersedes the emergency rule is adopted by the commission under IC 4-22-2-24 through IC 4-22-2-36.
(2) Modify the required reservation of capacity under the limit described in subdivision (1) to require the reservation of: (A) forty percent (40%) of the capacity for participation by residential customers; and (B) fifteen percent (15%) of the capacity for participation by customers that install a net metering facility that uses a renewable energy resource described in IC 8-1-37-4(a)(5).

Official source: Indiana General Assembly. Reproduced from public-domain Indiana statutes; confirm against the official source for the current text. Not legal advice.