Ind. Code § 8-1-8.4-2

"Compliance project"

Redline — January 1, 2018 → current.View current text →
Current — January 1, 2023
As of January 1, 2018
Sec. 2. (a) As used in this chapter, "compliance project" means a project that is:
Sec. 2. (a) As used in this chapter, "compliance project" means a project:
(1) undertaken by an energy utility; and
(1) undertaken by an energy utility; and
(2) related to the direct or indirect compliance by the energy utility with one (1) or more federally mandated requirements.
(2) related to the direct or indirect compliance by the energy utility with one (1) or more federally mandated requirements.
(b) The term includes:
(b) The term includes:
(1) an addition; or
(1) an addition; or
(2) an integrity, enhancement, or a replacement project;
(2) an integrity, enhancement, or a replacement project;
undertaken by an energy utility to comply with a federally mandated requirement described in section 5(5) of this chapter.
undertaken by an energy utility to comply with a federally mandated requirement described in section 5(5) of this chapter.

Official source: Indiana General Assembly. Reproduced from public-domain Indiana statutes; confirm against the official source for the current text. Not legal advice.