Ind. Code § 8-23-9-4
Acceptance of proposals; criteria
Redline — January 1, 2018 → current.View current text →
Current — January 1, 2023
As of January 1, 2018
Sec. 4. Notwithstanding any other statute or rule adopted by the department, the department may accept a proposal and award a contract for the construction, improvement, or maintenance of a road if:
Sec. 4. Notwithstanding any other statute or rule adopted by the department, the department may accept a proposal and award a contract for the construction, improvement, or maintenance of a road if:
(1) the lowest responsive and qualified bid is: (A) less than one million dollars ($1,000,000); (B) one (1) of four (4) or more bids received by the department for the contract; or (C) not more than fifteen percent (15%) above the estimated cost of the project;
(1) the lowest responsive and qualified bid is: (A) less than three million dollars ($3,000,000); (B) one (1) of three (3) or more bids received by the department for the contract; or (C) not more than fifteen percent (15%) above the estimated cost of the project;
(2) the commissioner believes that awarding a contract under this section is in the best interests of the state; and
(2) the commissioner believes that awarding a contract under this section is in the best interests of the state; and
(3) the award would comply with any requirement imposed under section 13 of this chapter.
(3) the award would comply with any requirement imposed under section 13 of this chapter.