N.Y. Gen. Bus. Law § 756-c

Retention

Showing this section's text as in effect on January 1, 2015 (in force January 1, 2015 – January 1, 2024). View current text →

§ 756-c. Retention. By mutual agreement of the relevant parties an\nowner may retain a reasonable amount of the contract sum as retainage. A\ncontractor or subcontractor may also retain a reasonable amount for\nretainage so long as the amount does not exceed the actual percentage\nretained by the owner. Retainage shall be released by the owner to the\ncontractor no later than thirty days after the final approval of the\nwork under a construction contract. In the event that an owner fails to\nrelease retainage as required by this article, or the contractor or\nsubcontractor fails to release a proportionate amount of retainage to\nthe relevant parties after receipt of retainage from the owner, the\nowner, contractor, or subcontractor, as the case may be, shall be\nsubject to the payment of interest at the rate of one percent per month\non the date retention was due and owing.\n

Official source: NYS Open Legislation (New York State Senate). Reproduced from public-domain New York statutes; confirm against the official source for the current text. Not legal advice.