Vt. Stat. Ann. tit. 24, § 4303a

Computation of time

Redline — July 1, 2021 → current.View current text →
Current — June 1, 2022
As of July 1, 2021
Where an event is required or permitted to occur by this chapter before, on, or after a specified period of time measured from another event, in calculating the period:
Where an event is required or permitted to occur by this chapter before, on, or after a specified period of time measured from another event, in calculating the period:
(1) the first day shall not be counted; and
(1) the first day shall not be counted; and
(2) the final day shall be counted. Added 1981, No. 132 (Adj. Sess.), § 3.
(2) the final day shall be counted.