10 U.S.C. § 18233A

Section 18233a · Notice and wait requirements for certain projects

Current version, with additions and removals from the October 30, 2000 version.

Current — November 25, 2015
As of October 30, 2000
(a)(1) Except as provided in paragraph (2), an expenditure or contribution in an amount in excess of $1,500,000 may not be made under section 18233 of this title for any facility until the Secretary of Defense has notified the Committee on Armed Services and the Committee on Appropriations of the Senate and the Committee on Armed Services and the Committee on Appropriations of the House of Representatives of the location, nature, and estimated cost of the facility and a period of 21 days has passed after receipt of such notification.
(a) Congressional Notification.—Except as provided in subsection (b), an expenditure or contribution in excess of the amount specified in section 2805(b)(1) of this title may not be made under section 18233 of this title for any facility until—

(1) the Secretary of Defense has notified the congressional defense committees of the location, nature, and estimated cost of the facility; and

(2) a period of 21 days has elapsed after the notification has been received by those committees or, if over sooner, a period of 14 days has elapsed after the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title.

(2) Paragraph (1) does not apply to expenditures or contributions for the following:
(b) Certain Expenditures or Contributions Exempted.—Subsection (a) does not apply to expenditures or contributions for the following:
(A) Facilities acquired by lease.
(1) Facilities acquired by lease.
(B) A project for a facility that has been authorized by Congress, if the location and purpose of the facility are the same as when authorized and if, based upon bids received—
(2) A project for a facility that has been authorized by Congress, if the location and purpose of the facility are the same as when authorized and if, based upon bids received—
(i) the scope of work of the project, as approved by Congress, is not proposed to be reduced by more than 25 percent; and
(A) the scope of work of the project, as approved by Congress, is not proposed to be reduced by more than 25 percent; and
(ii) the current working estimate of the cost of the project does not exceed the amount approved for the project by more than (I) 25 percent, or (II) 200 percent of the amount specified by section 2805(a)(2) of this title as the maximum amount for a minor military construction project, whichever is lesser.
(B) the current working estimate of the cost of the project does not exceed the amount approved for the project by more than the lesser of the following:

(C) An unspecified minor military construction project (as defined in section 2805(a) of this title) that is intended solely to correct a deficiency that is life-threatening, health-threatening, or safety-threatening.

(b) Under such regulations as the Secretary of Defense may prescribe, the Secretary may spend, from appropriations available for operation and maintenance, amounts necessary to carry out any project authorized under section 18233(a) of this title costing not more than—

(1) the amount specified in section 2805(c)(1)(A) of this title, in the case of a project intended solely to correct a deficiency that is life-threatening, health-threatening, or safety-threatening; or

(2) the amount specified in section 2805(c)(1)(B) of this title, in the case of any other project.

(i) 25 percent.

(ii) 200 percent of the amount specified by section 2805(a) of this title as the maximum amount for a minor military construction project.

(3) A repair project (as that term is defined in subsection (e) of section 2811 of this title) that costs less than the amount specified in subsection (d) of such section.