(a) In General.—The Director of Cost Assessment and Program Evaluation shall ensure that the cost estimation and cost analysis processes of the Department of Defense provide accurate information and realistic estimates of cost for the acquisition programs of the Department of Defense. In carrying out that responsibility, the Director shall—
(a) In General.—The Director of Cost Assessment and Program Evaluation shall ensure that the cost estimation and cost analysis processes of the Department of Defense provide accurate information and realistic estimates of cost for the acquisition programs of the Department of Defense. In carrying out that responsibility, the Director shall—
(1) prescribe, by authority of the Secretary of Defense, policies and procedures for the conduct of cost estimation and cost analysis for the acquisition programs of the Department of Defense;
(1) prescribe, by authority of the Secretary of Defense, policies and procedures for the conduct of cost estimation and cost analysis for the acquisition programs of the Department of Defense;
(A) in advance of—
(A) in advance of—
(ii) any decision to enter into low-rate initial production or full-rate production;
(ii) any decision to enter into low-rate initial production or full-rate production;
(iii) any certification under section 2433a of this title; and
(iii) any certification under section 2433a of this title; and
(iv) any report under section 2445c(f) of this title; and
(iv) any report under section 2445c(f) of this title; and
(8) annually review the cost and associated information required to be included, by section 2432(c)(1) of this title, in the Selected Acquisition Reports required by that section.
(b) Independent Cost Estimate Required Before Approval.—(1) A milestone decision authority may not approve entering a milestone phase of a major defense acquisition program or major subprogram unless an independent cost estimate has been conducted or approved by the Director of Cost Assessment and Program Evaluation and considered by the milestone decision authority that—
(A) for the technology maturation and risk reduction phase, includes the identification and sensitivity analysis of key cost drivers that may affect life-cycle costs of the program or subprogram; and
(B) for the engineering and manufacturing development phase, or production and deployment phase, includes a cost estimate of the full life-cycle cost of the program or subprogram.
(2) The regulations governing the content and submission of independent cost estimates required by subsection (a) shall require that the independent cost estimate of the full life-cycle cost of a program or subprogram include—
(A) all costs of development, procurement, military construction, operations and support, and trained manpower to operate, maintain, and support the program or subprogram upon full operational deployment, without regard to funding source or management control; and
(B) an analysis to support decisionmaking that identifies and evaluates alternative courses of action that may reduce cost and risk, and result in more affordable programs and less costly systems.
(2) has timely access to any records and data in the Department of Defense (including the records and data of each military department and Defense Agency and including classified and proprietary information) that the Director considers necessary to review in order to carry out any duties under this section.
(2) has timely access to any records and data in the Department of Defense (including the records and data of each military department and Defense Agency and including classified and proprietary information) that the Director considers necessary to review in order to carry out any duties under this section.
(1) disclose in accordance with paragraph (3) the confidence level used in establishing a cost estimate for a major defense acquisition program or major automated information system program and the rationale for selecting such confidence level;
(1) issue guidance requiring a discussion of risk, the potential impacts of risk on program costs, and approaches to mitigate risk in cost estimates for major defense acquisition programs and major subprograms;
(A) in any decision documentation approving a cost estimate within the baseline description or any other cost estimate for use at any event specified in subsection (a)(6); and
(A) in any decision documentation approving a cost estimate within the baseline description or any other cost estimate for use at any event specified in subsection (a)(6); and
(A) cost estimates developed for baseline descriptions and other program purposes conducted pursuant to subsection (a)(6) are not to be used for the purpose of contract negotiations or the obligation of funds; and
(A) may be used—
(A) may be used—
(i) to cover any increased program costs identified by a revised cost analysis or target developed pursuant to paragraph (2);
(i) to cover any increased program costs identified by a revised cost analysis or target developed pursuant to paragraph (2);
(ii) to acquire additional end items in accordance with the requirements of section 2308 of this title; or
(ii) to acquire additional end items in accordance with the requirements of section 2308 of this title; or
(iii) to cover the cost of risk reduction and process improvements; and
(iii) to cover the cost of risk reduction and process improvements; and
(B) may be reprogrammed, in accordance with established procedures, only if determined to be excess to program needs on the basis of a cost estimate developed with the concurrence of the Director of Cost Assessment and Program Evaluation.
(B) may be reprogrammed, in accordance with established procedures, only if determined to be excess to program needs on the basis of a cost estimate developed with the concurrence of the Director of Cost Assessment and Program Evaluation.
(f) Annual Report on Cost Assessment Activities.—(1) The Director of Cost Assessment and Program Evaluation shall prepare an annual report summarizing the cost estimation and cost analysis activities of the Department of Defense during the previous year and assessing the progress of the Department in improving the accuracy of its cost estimates and analyses. Each report shall include, for the year covered by such report, an assessment of—
(A) the extent to which each of the military departments and Defense Agencies have complied with policies, procedures, and guidance issued by the Director with regard to the preparation of cost estimates for major defense acquisition programs and major automated information systems;
(B) the overall quality of cost estimates prepared by each of the military departments and Defense Agencies for major defense acquisition programs and major automated information system programs; and
(C) any consistent differences in methodology or approach among the cost estimates prepared by the military departments, the Defense Agencies, and the Director.
(2) Each report under this subsection shall be submitted concurrently to the Secretary of Defense, the Under Secretary of Defense for Acquisition, Technology, and Logistics, the Under Secretary of Defense (Comptroller), and the congressional defense committees not later than 10 days after the transmittal to Congress of the budget of the President for the next fiscal year (as submitted pursuant to section 1105 of title 31).
(3)(A) Each report submitted to the congressional defense committees under this subsection shall be submitted in unclassified form, but may include a classified annex.
(B) The Director shall ensure that a report submitted under this subsection does not include any information, such as proprietary or source selection sensitive information, that could undermine the integrity of the acquisition process.
(C) The unclassified version of each report submitted to the congressional defense committees under this subsection shall be posted on an Internet website of the Department of Defense that is available to the public.
(4) The Secretary of Defense may comment on any report of the Director to the congressional defense committees under this subsection.
(g) Guidelines and Collection of Cost Data.—(1) The Director of Cost Assessment and Program Evaluation shall, in consultation with the Under Secretary of Defense for Acquisition and Sustainment, develop policies, procedures, guidance, and a collection method to ensure that quality acquisition cost data are collected to facilitate cost estimation and comparison across acquisition programs.
(2) The program manager and contracting officer for each acquisition program in an amount greater than $100,000,000, in consultation with the cost estimating component of the relevant military department or Defense Agency, shall ensure that cost data are collected in accordance with the requirements of paragraph (1).
(3) The requirement under paragraph (1) may be waived only by the Director of Cost Assessment and Program Evaluation.