10 U.S.C. § 2431
Section 2431 · Weapons development and procurement schedules
Current version, with additions and removals from the October 13, 1994 version.
(a) The Secretary of Defense shall submit to Congress each calendar year, not later than 45 days after the President submits the budget to Congress under section 1105 of title 31, budget justification documents regarding development and procurement schedules for each weapon system for which fund authorization is required by section 114(a) of this title, and for which any funds for procurement are requested in that budget. The documents shall include data on operational testing and evaluation for each weapon system for which funds for procurement are requested (other than funds requested only for the procurement of units for operational testing and evaluation, or long lead-time items, or both). A weapon system shall also be included in the annual documents required under this subsection in each year thereafter until procurement of that system has been completed or terminated, or the Secretary of Defense certifies, in writing, that such inclusion would not serve any useful purpose and gives his reasons therefor.
(a) The Secretary of Defense shall submit to Congress each calendar year, not later than 45 days after the President submits the budget to Congress under section 1105 of title 31, budget justification documents regarding development and procurement schedules for each weapon system for which fund authorization is required by section 114(a) of this title, and for which any funds for procurement are requested in that budget. The documents shall include data on operational testing and evaluation for each weapon system for which funds for procurement are requested (other than funds requested only for the procurement of units for operational testing and evaluation, or long lead-time items, or both). A weapon system shall also be included in the annual documents required under this subsection in each year thereafter until procurement of that system has been completed or terminated, or the Secretary of Defense certifies, in writing, that such inclusion would not serve any useful purpose and gives his reasons therefor.
(1) The development schedule, including estimated annual costs until development is completed.
(1) The development schedule, including estimated annual costs until development is completed.
(2) The planned procurement schedule, including the best estimate of the Secretary of Defense of the annual costs and units to be procured until procurement is completed.
(2) The planned procurement schedule, including the best estimate of the Secretary of Defense of the annual costs and units to be procured until procurement is completed.
(4)(A) The most efficient production rate, the most efficient acquisition rate, and the minimum sustaining rate, consistent with the program priority established for such weapon system by the Secretary concerned.
(4)(A) The most efficient production rate, the most efficient acquisition rate, and the minimum sustaining rate, consistent with the program priority established for such weapon system by the Secretary concerned.
(B) In this paragraph:
(B) In this paragraph:
(i) The term “most efficient production rate” means the maximum rate for each budget year at which the weapon system can be produced with existing or planned plant capacity and tooling, with one shift a day running for eight hours a day and five days a week.
(i) The term “most efficient production rate” means the maximum rate for each budget year at which the weapon system can be produced with existing or planned plant capacity and tooling, with one shift a day running for eight hours a day and five days a week.
(ii) The term “minimum sustaining rate” means the production rate for each budget year that is necessary to keep production lines open while maintaining a base of responsive vendors and suppliers.
(ii) The term “minimum sustaining rate” means the production rate for each budget year that is necessary to keep production lines open while maintaining a base of responsive vendors and suppliers.