10 U.S.C. § 2433
Section 2433 · Unit cost reports
Current version, with additions and removals from the November 18, 1997 version.
(a) In this section:
(a) In this section:
(3) The term “procurement program” means a program for which funds for procurement are authorized to be appropriated in a fiscal year.
(3) The term "procurement program" means a program for which funds for procurement are authorized to be appropriated in a fiscal year.
(4) The term "significant cost growth threshold" means the following:
(A) In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(i) at least 15 percent over the program acquisition unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
(ii) at least 30 percent over the program acquisition unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
(B) In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
(i) at least 15 percent over the procurement unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
(ii) at least 30 percent over the procurement unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
(5) The term "critical cost growth threshold" means the following:
(A) In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(i) at least 25 percent over the program acquisition unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
(ii) at least 50 percent over the program acquisition unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
(B) In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
(i) at least 25 percent over the procurement unit cost for the program or subprogram as shown in the current Baseline Estimate for the program or subprogram; or
(ii) at least 50 percent over the procurement unit cost for the program or subprogram as shown in the original Baseline Estimate for the program or subprogram.
(6) The term "original Baseline Estimate" has the same meaning as provided in section 2435(d) of this title.
(3) Any cost variance or schedule variance in a major contract under the program since the contract was entered into.
(3) Any cost variance or schedule variance in a major contract under the program since the contract was entered into.
(4) Any changes from program schedule milestones or program performances reflected in the baseline description established under section 2435 of this title that are known, expected, or anticipated by the program manager.
(4) Any changes from program schedule milestones or program performances reflected in the baseline description established under section 2435 of this title that are known, expected, or anticipated by the program manager.
(c) If the program manager of a major defense acquisition program for which a unit cost report has previously been submitted under subsection (b) determines at any time during a quarter that there is reasonable cause to believe—
(1) that the program acquisition unit cost for the program has increased by at least 15 percent over the program acquisition unit cost for the program as shown in the Baseline Estimate; or
(2) in the case of a major defense acquisition program that is a procurement program, that the procurement unit cost for the program has increased by at least 15 percent over the procurement unit cost for the program as reflected in the Baseline Estimate;
(5) Any significant changes in the total program cost for development and procurement of the software component of the program or subprogram, schedule milestones for the software component of the program or subprogram, or expected performance for the software component of the program or subprogram that are known, expected, or anticipated by the program manager.
(A) a written certification, stating that—
(i) such acquisition program is essential to the national security;
(ii) there are no alternatives to such acquisition program which will provide equal or greater military capability at less cost;
(iii) the new estimates of the program acquisition unit cost or procurement unit cost are reasonable; and
(iv) the management structure for the acquisition program is adequate to manage and control program acquisition unit cost or procurement unit cost; and
(B) if a report under paragraph (1) has been previously submitted to Congress with respect to such program for the current fiscal year but was based upon a different unit cost report from the program manager to the service acquisition executive designated by the Secretary concerned, a further report containing the information described in subsection (g), determined from the time of the previous report to the time of the current report.
(f) Any determination of a percentage increase under this section shall be stated in terms of constant base year dollars (as described in section 2430 of this title).
(f) Any determination of a percentage increase under this section shall be stated in terms of constant base year dollars (as described in section 2430 of this title).
(g)(1) Except as provided in paragraph (2), each report under subsection (e) with respect to a major defense acquisition program shall include the following:
(g)(1) Except as provided in paragraph (2), each report under subsection (e) with respect to a major defense acquisition program shall include the following:
(A) The name of the major defense acquisition program.
(A) The name of the major defense acquisition program.
(B) The date of the preparation of the report.
(B) The date of the preparation of the report.
(C) The program phase as of the date of the preparation of the report.
(C) The program phase as of the date of the preparation of the report.
(I) The type of the Baseline Estimate that was included in the baseline description under section 2435 of this title and the date of the Baseline Estimate.
(I) The type of the Baseline Estimate that was included in the baseline description under section 2435 of this title and the date of the Baseline Estimate.
(L) The quantity of end items to be acquired under the program and the current change and total change, if any, in that quantity.
(L) The quantity of end items to be acquired under the program and the current change and total change, if any, in that quantity.
(M) The identities of the military and civilian officers responsible for program management and cost control of the program.
(M) The identities of the military and civilian officers responsible for program management and cost control of the program.
(N) The action taken and proposed to be taken to control future cost growth of the program.
(N) The action taken and proposed to be taken to control future cost growth of the program.
(i) The name of the contractor.
(i) The name of the contractor.
(ii) The phase that the contract is in at the time of the preparation of the report.
(ii) The phase that the contract is in at the time of the preparation of the report.
(iii) The percentage of work under the contract that has been completed.
(iii) The percentage of work under the contract that has been completed.
(iv) Any current change and the total change, in dollars and expressed as a percentage, in the contract cost.
(iv) Any current change and the total change, in dollars and expressed as a percentage, in the contract cost.
(v) The percentage by which the contract is currently ahead of or behind schedule.
(v) The percentage by which the contract is currently ahead of or behind schedule.
(Q) In any case in which one or more problems with the software component of the program or any designated major subprogram under the program significantly contributed to the increase in program unit costs, the action taken and proposed to be taken to solve such problems.
(h) Reporting under this section shall not apply if a program has received a limited reporting waiver under section 2432(h) of this title.
(h) Reporting under this section shall not apply if a program has received a limited reporting waiver under section 2432(h) of this title.