42 U.S.C. § 17384
Section 17384 · Smart grid technology research, development, and demonstration
Current version, with additions and removals from the February 17, 2009 version.
(1) to develop advanced techniques for measuring peak load reductions and energy-efficiency savings from smart metering, demand response, distributed generation, and electricity storage systems;
(1) to develop advanced techniques for measuring peak load reductions and energy-efficiency savings from smart metering, demand response, distributed generation, and electricity storage systems;
(2) to investigate means for demand response, distributed generation, and storage to provide ancillary services;
(2) to investigate means for demand response, distributed generation, and storage to provide ancillary services;
(3) to conduct research to advance the use of wide-area measurement and control networks, including data mining, visualization, advanced computing, and secure and dependable communications in a highly-distributed environment;
(3) to conduct research to advance the use of wide-area measurement and control networks, including data mining, visualization, advanced computing, and secure and dependable communications in a highly-distributed environment;
(4) to test new reliability technologies, including those concerning communications network capabilities, in a grid control room environment against a representative set of local outage and wide area blackout scenarios;
(4) to test new reliability technologies, including those concerning communications network capabilities, in a grid control room environment against a representative set of local outage and wide area blackout scenarios;
(5) to identify communications network capacity needed to implement advanced technologies.1
(5) to identify communications network capacity needed to implement advanced technologies.1
(6) to investigate the feasibility of a transition to time-of-use and real-time electricity pricing;
(6) to investigate the feasibility of a transition to time-of-use and real-time electricity pricing;
(7) to develop algorithms for use in electric transmission system software applications;
(7) to develop algorithms for use in electric transmission system software applications;
(8) to promote the use of underutilized electricity generation capacity in any substitution of electricity for liquid fuels in the transportation system of the United States; and
(8) to promote the use of underutilized electricity generation capacity in any substitution of electricity for liquid fuels in the transportation system of the United States; and
(9) in consultation with the Federal Energy Regulatory Commission, to propose interconnection protocols to enable electric utilities to access electricity stored in vehicles to help meet peak demand loads.
(9) in consultation with the Federal Energy Regulatory Commission, to propose interconnection protocols to enable electric utilities to access electricity stored in vehicles to help meet peak demand loads.
(1) In general
(1) In general
(2) Goals
(2) Goals
The goals of the Initiative shall be—
The goals of the Initiative shall be—
(A) to demonstrate the potential benefits of concentrated investments in advanced grid technologies on a regional grid;
(A) to demonstrate the potential benefits of concentrated investments in advanced grid technologies on a regional grid;
(B) to facilitate the commercial transition from the current power transmission and distribution system technologies to advanced technologies;
(B) to facilitate the commercial transition from the current power transmission and distribution system technologies to advanced technologies;
(C) to facilitate the integration of advanced technologies in existing electric networks to improve system performance, power flow control, and reliability;
(C) to facilitate the integration of advanced technologies in existing electric networks to improve system performance, power flow control, and reliability;
(F) to encourage the commercial application of advanced distribution automation technologies that exert intelligent control over electrical grid functions at the distribution level to improve system resilience.
(3) Demonstration projects
(3) Demonstration projects
(A) In general
(A) In general
In carrying out the initiative,2 the Secretary shall provide financial support to smart grid demonstration projects in urban, suburban, tribal, and rural areas, including areas where electric system assets are controlled by nonprofit entities and areas where electric system assets are controlled by investor-owned utilities.
In carrying out the initiative,2 the Secretary shall provide financial support to smart grid demonstration projects in urban, suburban, tribal, and rural areas, including areas where electric system assets are controlled by nonprofit entities and areas where electric system assets are controlled by investor-owned utilities.
(B) Cooperation
(B) Cooperation
A demonstration project under subparagraph (A) shall be carried out in cooperation with the electric utility that owns the grid facilities in the electricity control area in which the demonstration project is carried out.
A demonstration project under subparagraph (A) shall be carried out in cooperation with the electric utility that owns the grid facilities in the electricity control area in which the demonstration project is carried out.
(C) Federal share of cost of technology investments
(C) Federal share of cost of technology investments
The Secretary shall provide to an electric utility described in subparagraph (B) or to other parties financial assistance for use in paying an amount equal to not more than 50 percent of the cost of qualifying advanced grid technology investments made by the electric utility or other party to carry out a demonstration project.
The Secretary shall provide to an electric utility described in subparagraph (B) or to other parties financial assistance for use in paying an amount equal to not more than 50 percent of the cost of qualifying advanced grid technology investments made by the electric utility or other party to carry out a demonstration project.
(D) Ineligibility for grants
(D) Ineligibility for grants
No person or entity participating in any demonstration project conducted under this subsection shall be eligible for grants under section 17386 of this title for otherwise qualifying investments made as part of that demonstration project.
No person or entity participating in any demonstration project conducted under this subsection shall be eligible for grants under section 17386 of this title for otherwise qualifying investments made as part of that demonstration project.
(E) Availability of data
(E) Availability of data
The Secretary shall establish and maintain a smart grid information clearinghouse in a timely manner which will make data from smart grid demonstration projects and other sources available to the public. As a condition of receiving financial assistance under this subsection, a utility or other participant in a smart grid demonstration project shall provide such information as the Secretary may require to become available through the smart grid information clearinghouse in the form and within the timeframes as directed by the Secretary. The Secretary shall assure that business proprietary information and individual customer information is not included in the information made available through the clearinghouse.
The Secretary shall establish and maintain a smart grid information clearinghouse in a timely manner which will make data from smart grid demonstration projects and other sources available to the public. As a condition of receiving financial assistance under this subsection, a utility or other participant in a smart grid demonstration project shall provide such information as the Secretary may require to become available through the smart grid information clearinghouse in the form and within the timeframes as directed by the Secretary. The Secretary shall assure that business proprietary information and individual customer information is not included in the information made available through the clearinghouse.
(F) Open protocols and standards
(F) Open protocols and standards
The Secretary shall require as a condition of receiving funding under this subsection that demonstration projects utilize open protocols and standards (including Internet-based protocols and standards) if available and appropriate.
The Secretary shall require as a condition of receiving funding under this subsection that demonstration projects utilize open protocols and standards (including Internet-based protocols and standards) if available and appropriate.
There are authorized to be appropriated—
There are authorized to be appropriated—
(1) to carry out subsection (a), such sums as are necessary for each of fiscal years 2008 through 2012; and
(1) to carry out subsection (a), such sums as are necessary for each of fiscal years 2008 through 2012; and
(2) to carry out subsection (b), such sums as may be necessary.
(2) to carry out subsection (b), such sums as may be necessary.