Public-domain · open source
OpenJurist

49 U.S.C. § 5327

Section 5327 · Project management oversight

Current version, with additions and removals from the June 9, 1998 version.

Current — December 4, 2015
As of June 9, 1998
(a) Project Management Plan Requirements.—To receive United States Government financial assistance for a major capital project under this chapter or the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), a recipient must prepare and carry out a project management plan approved by the Secretary of Transportation. The plan shall provide for—
(a) Project Management Plan Requirements.—To receive Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan. The plan shall provide for—

(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;

(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;

(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;

(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;

(3) a construction schedule for the project;

(3) a construction schedule for the project;

(4) a document control procedure and recordkeeping system;

(4) a document control procedure and recordkeeping system;

(5) a change order procedure that includes a documented, systematic approach to the handling of construction change orders;

(5) a change order procedure that includes a documented, systematic approach to the handling of construction change orders;

(6) organizational structures, management skills, and staffing levels required throughout the construction phase;

(6) organizational structures, management skills, and staffing levels required throughout the construction phase;

(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;

(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;

(8) material testing policies and procedures;

(8) material testing policies and procedures;

(9) internal plan implementation and reporting requirements;

(9) internal plan implementation and reporting requirements;

(10) criteria and procedures to be used for testing the operational system or its major components;

(10) criteria and procedures to be used for testing the operational system or its major components;

(11) periodic updates of the plan, especially related to project budget and project schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts; and
(11) periodic updates of the plan, especially related to project budget and project schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts;
(12) the recipient's commitment to submit a project budget and project schedule to the Secretary each month.
(12) the recipient's commitment to submit a project budget and project schedule to the Secretary quarterly; and

(13) safety and security management.

(b) Plan Approval.—(1) The Secretary shall approve a plan not later than 60 days after it is submitted. If the approval cannot be completed within 60 days, the Secretary shall notify the recipient, explain the reasons for the delay, and estimate the additional time that will be required.

(b) Plan Approval.—(1) The Secretary shall approve a plan not later than 60 days after it is submitted. If the approval cannot be completed within 60 days, the Secretary shall notify the recipient, explain the reasons for the delay, and estimate the additional time that will be required.

(2) The Secretary shall inform the recipient of the reasons when a plan is disapproved.

(2) The Secretary shall inform the recipient of the reasons when a plan is disapproved.

(c) Limitations on Use of Available Amounts.—(1) The Secretary may use not more than .5 percent of amounts made available for a fiscal year to carry out section 5307, 5309, or 5311 of this title, an interstate transfer mass transportation project under section 103(e)(4) 1 of title 23 as in effect on September 30, 1991, or a project under the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320) to make a contract to oversee the construction of a major project under section 5307, 5309, 5311, or 103(e)(4) 1 or that Act. The Secretary may use when necessary not more than an additional .25 percent of amounts made available in a fiscal year to carry out a major project under section 5309 to make a contract to oversee the construction of the project.

(2) The Secretary may use amounts available under paragraph (1) of this subsection to enter into contracts for safety, procurement, management, and financial compliance reviews and audits of a recipient of amounts under paragraph (1) and to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section. Subsections (a), (b), and (e) of this section do not apply to contracts under this paragraph.

(3) The Government shall pay the entire cost of carrying out a contract under this subsection.

(d) Access to Sites and Records.—Each recipient of assistance under this chapter or section 14(b) of the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), as added by section 2 of the National Capital Transportation Amendments of 1979 (Public Law 96–184, 93 Stat. 1320), shall provide the Secretary and a contractor the Secretary chooses under subsection (c) of this section with access to the construction sites and records of the recipient when reasonably necessary.
(c) Access to Sites and Records.—Each recipient of Federal financial assistance for public transportation under this chapter or any other provision of Federal law shall provide the Secretary and a contractor the Secretary chooses under section 5338(f) with access to the construction sites and records of the recipient when reasonably necessary.
(e) Regulations.—The Secretary shall prescribe regulations necessary to carry out this section. The regulations shall include—
(d) Regulations.—The Secretary shall prescribe regulations necessary to carry out this section. The regulations shall include—
(1) a definition of "major capital project" for subsection (c) of this section that excludes a project to acquire rolling stock or to maintain or rehabilitate a vehicle; and
(1) a definition of "major capital project" for section 5338(f) that excludes a project to acquire rolling stock or to maintain or rehabilitate a vehicle;

(2) a requirement that oversight—

(2) a requirement that oversight begin during the preliminary engineering stage of a project, unless the Secretary finds it more appropriate to begin the oversight during another stage of the project, to maximize the transportation benefits and cost savings associated with project management oversight.
(A) begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight; and

(f) Financial Plan.—A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.

(B) be limited to quarterly reviews of compliance by the recipient with the project management plan approved under subsection (b) unless the Secretary finds that the recipient requires more frequent oversight because the recipient has failed to meet the requirements of such plan and the project may be at risk of going over budget or becoming behind schedule; and

(3) a process for recipients that the Secretary has found require more frequent oversight to return to quarterly reviews for purposes of paragraph (2)(B).

/49/usc/5327 · .json · Public domain