Public-domain · open source
OpenJurist

96 U.S. 424

Walker v. Johnson

Supreme Court of the United States

Decided October 1, 1877

Supreme Court of the United States · decided 1877-10

On the twenty-first day of July,- 1869, Edwin 1. Sherburne, Edwin Walker, and Charles B. Farwell entered into a written 'contract with the canal commissioners of the State of Illinois, for the construction of a lock and dam in the Illinois River, near the city of Henry, in which they agreed to commence the work on or before the first day of August, 1869, and complete it by the first day' of September, 1871.

2 counsel of record

Key passage — most relied on by later courts

““§ 500'. Contracts not intended to be performed within a year. “Another fine but important distinction is between: “1. A contract which can be performed, as the parties intend that it shall be performed, within a year, though they fully expect that performance will take a longer period and “2. A contract which cannot be performed within a year, as the parties intend and expect that it shall be performed, though performance in a different way within that time is conceivably possible and if so made would satisfy the literal words of the contract. “Contracts of the first sort are not within the Statute; those of the second sort are held at least by many courts to be within the Statute. The opinion of the parties as to the time which a given performance will take is immaterial, but their mutual in- . tentions as to the method of performance is important, and if that method cannot possibly be carried out within a year, the fact that another method which would satisfy the legal obligation is logically conceivable will not save the contract. * * * * # ft * “But in some of the cases hereafter referred to, it seems that performance of the contracts in question if completed within a year, could not have been objected to; and the contracts were nevertheless held within the Statute because performance in the way intended and expected, though not specially contracted for, could not be made within a year. ‘Of course, it was. possible the contract here could have been performed within a yea”

quoted by 1 later decision, including Markowitz Bros. v. John A. Volpe Construction Co.

““In order to bring a contract within the infra annum clause, it must appear affirmatively that it is not to be performed within the year. And it has been said that the purpose of the statute is to provide only for a case in which there cannot be an actionable breach within the specified time. So it is the generally accepted rule that to bring a contract within its operation there must be an express and specified agreement not to be performed within the space of a year; if the thing may be performed within the year, it is not, within the statute, a restricted construction being given to the statute on account of the negative form of the provision. A contract is not brought within the statute by the fact that the full performance within a year is highly improbable, nor by the fact that the parties may not have expected that the contract would be performed within the year. This is said to be true if there is a possibility of its being performed within a year, and there is no stipulation that it shall not be so performed. If an agreement is capable of being performed within a year it is not within the statute, although it be not actually .performed till after that period, and after the expiration of the year it still remains binding.””

quoted by 1 later decision, including Municipal Gas Co. v. Gilkerson

Relies on Packet Company v. Sickles · Swain v. Seamens · Kent v. . Kent

Good law ✅— No negative treatment on recordhow we know

Affirmed · 9–0 · Decided 1877-10

How this case has been cited

Cited by 40 later decisions (1 by the Supreme Court) — most recently December 1991 · most notably Warner v. Texas P Ry Co (1896), C. R. Klewin, Inc. v. Flagship Properties, Inc. (1991)

4 federal appellate · 30 state decisions — followed in 12 states

1101877188018901900191019201930194019501960197019801990decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

¶11. A parol Contract for the delivery of materials is not void under the Statute of Frauds, unless it appears affirmatively that it was not to be performed within a year. If performance by the promisor can be required by the promisee within a year, the contract is valid.

¶2% A subsequent verbal agreement varying the manner of delivering them is binding.

¶33. The comments of the judge in his charge to the jury, as to the circumstances under which the defendant might be entitled to damages against’the plaintiff, cannot be a ground of error, when there was no such issue, and when the defendant could not have been thereby prejudiced.

¶44. The court is not bound, at the request of counsel, to give as instructions philosophical remarks copied from text-books, however wise or true they may be in the abstract, or however' high the reputation of the authors. .

¶5Error to the Circuit Court of the United, States for the Northern District of Illinois.

¶6On the twenty-first day of July,- 1869, Edwin 1. Sherburne, Edwin Walker, and Charles B. Farwell entered into a written 'contract with the canal commissioners of the State of Illinois, for the construction of a lock and dam in the Illinois River, near the city of Henry, in which they agreed to commence the work on or before the first day of August, 1869, and complete it by the first day' of September, 1871.

¶7*425Sherburne shortly after assigned his interest in this contract to James K. Lake, and Lake, Farwell, and Walker assigned, the - same, with the approval of the commissioners, to Willard Johnson, plaintiff below.- But while Farwell, Lake, and.Walker, were the contractors, they made an- agreement between themselves, in writing, by which, among other .things, Walker was “ to furnish all the stone necessary for the construction of the lock and dam, to be by him’ delivered on board of canal-boats at Henry, as the same might be required in the progress of the work, to be of the description required for said work; ’’ and the prices that he was to receive for the various kinds of stone so delivered were settled. It is alleged by Johnson, that, after • the contract with the commissioners had been assigned to him, Walker agreed with him to furnish the stone for the work in the same manner and on the same terms as in this contract with his former partners. And that, by reason of his failure to do so, he, the plaintiff, was greatly damaged; and for that he brought this action. A verdict and' judgment for $6,500 were rendered against defendant Walker, to which he prosecutes the present writ of error.

¶8The .errors assigned relate exclusively to exceptions taken to the charge of the judge, and to his refusal to charge as requested by the defendant. They are fully stated in the opinion of the court.

¶9Mr. Melville W. Fuller for the plaintiff in error.

¶10The contract was void under the Statute of Frauds. Browne, Stat. Frauds, sects. 279, 283; Packet Company v. Sickles, 5 Wall. 580; Birch v. The Farl of Liverpool, 9 Barn. & Cress. 392; Dobson and Another v. Fspie, 2 H. & N., 81; Boydell v. Drummond, 11. East, 142.

¶11The alleged parol contract to deliver the stone by railroad, instead of by canal-boats as agreed upon in the original contract, was without consideration, and therefore void. Gross v. Nugent, 5 Barn. & Adol. 65; Lattimore v. Hensen, 14 Johns. . (N. Y.) 330; Munroe v. Perkins, 9 Pick. (Mass.) 295.; Adams v. Nichols, 19 id. 275; Crowley v. Vitley, 7 Ex. 319; Payne v. New. S. C. Coi, 10 id. 291; Thurston v. Ludwig, 6 Ohio St. 1; Hunt v. Barfield, 19 Ala. 117;. Gerhard v. Bates, 2 El. & Bl. 486; Swain v. Seamans, 9 Wall. 254.

¶12*426• It was also void, because' entered into aftér breach in the original contract.

¶13Mr. Francis Kernan, contra.

¶14If by the terms of a contract, the subject-matter, and the situation of the parties, it is shown that the contract can, and reasonably may in its execution, be required to be performed within a year, it is not within the Statute of Frauds. Browne, Stat. Frauds, sects. 274, 275, 278 a, 279, 281, 286, and cases cited; White v. Mwtland, 71 111. 250; Kent v. Kent, 62 N. Y. 564; Morley v. Noblett, 42 Ind. 85 ; Larimer y: Kelly, 10 Kan. 298; Cault y. Brown, 48 N. H. 183; Peters v. Westboro’, 19 Pick. (Mass.) 365; Blake v. Cole, 22 id. 99; Somerley v. Buntin, 118 Mass.-286;' Blair y. Walker, 39 Iowa, 410; Creene y. Harris, 9 R. I. 401; Hodges y. Richmond, id. 487; Souch v. Straivbridge, 2 O. B. 811; Plimpton v. Curtis, 15 Wend. (N. Y.) 336; Peter v. Compton, 1 Sm. L. C. 432..

¶15There was no error in the instruction of the court below,' that it was competent for the .parties to modify the terms of their original contract by agreeing that the stone should be delivered by railroad instead of by canal-boats. Their mutual promises were a sufficient consideration. Law v. Forbes, 18 111. 568; Bishop v. Bicsse, 69 id. 403; Cooke v. Murphy, 70 id. 96; Carrier v. Bilworth, 59 Pa. St. 406; Hill v. Smith, 34 Yt. 535; Monroe v. Perkins, 9 Pick. (Mass.) 298.

¶16Mr. -Justice Miller

¶17delivered the opinion of the court.

¶18The first error arises upon the proposition of defendant, that the contract, being one not to-be performed within a year from the time it was made, and resting only in parol,- was void, and could not sustain the action. Evidence was given which tended to show that the agreement between plaintiff and defendant was made early in November, 1869, and renewed or modified in April, 1870. As by the terms of the original contract with the canal commissioners the work was to be completed on or"before Sept. 1, 1871, defendant insisted that his contract for delivery .of stone' had the same time to run; and his counsel asked the court to .instruct the jury that it was void, if it appeared from the Far-well, Lake, and Walker contract that it was not the intention and understanding of the parties that the same should be per*427formed within the space of one year from the making of the verbal agreement between plaintiff and defendant.

¶19The court' refused this instruction, and told the jury that if it Appeared from the contract itself that it was not to be performed, or was not intended to be performed, within a year, it was void; but that if it .was a contract which might have been performed within á year, and which the plaintiff, at his option, might have required the defendant to perform within a year, it was not within the statute.

¶20We think the court ruled correctly, both in what it charged and in what it refused.

¶211. In order to bring a parol contract v/ithin the statute, it must appear affirmatively that the- contract was not to be performed within the year. Wé have had occasion to examine this question very recently in the ease of McPherson v. Cox (supra, p. 404). We said, in that case, that the statute “ applies only to contracts which, by their terms, are not to be performed within the.year, and not to contracts which may not be performed within that time.” The court said, in regard to that case, which was a contract by a lawyer to conduct, a suit in court, that there was nothing to show that it could not have been fully performed within a 'year. So, in this case, the lock and dam were to be compléted on or before Sept. 1, 1871. Clearly, the contractor had the right to push his work so as to finish it before November, 1870, which would have been within a yqar from the date of Walker’s contract with plaintiff. ■

¶22If plaintiff had a right to do his work within that time, he had a right to require of defendant to deliver the- stone necessary to enable him to do it. There is no error in the' action of the court on this branch of the subject.

¶232. It will be observed that, by the agreement of Walker with his partners, he was to deliver at Henry “in canal-boats. Evidence was given tending to show that, in the spring of 1870, it was agreed between him and plaintiff that he should deliver by railroad; and the court charged the jury that it was competent for the parties to change the contract in that regard, if they chose; and that if the jury found that defendant did so agree, he was bound by such agreement as he made, if any.

¶24The original contract between Johnson and Walker was in *428parol; and if the parties, for their mutual convenience, or for no good reason at all, chose a delivery by rail, both of- them consenting thereto, we think that the change in the mode of delivery became a part of the contract.

¶253. There was evidence tending to show that, while defendant was performing part of the contract, he received notice from plaintiff that he would take no more stone from him ; and also evidence that, shortly after this, the parties had an interview, in which this notice was waived, and Walker agreed to go on with the contract. On this part of the case the court said: —

“ If the testimony satisfies you that the defendant did, after the notice of the 12th of May, recognize the contract as still in force, and promise the .plaintiff that he would go on and complete the same, the defendant cannot-now claim as a defence to this action that, said notice released him from the performance of the contract.
“ If, on the contrary, you are satisfied that the defendant made no agreement after the notice to stop on the 12th of May, recognizing the contract as still in force, or promising to perform it or continue it in force, then the defence may be considered made out, although the notice to suspend might entitle the defendant to dama es; but I do. not think it necessary to discuss the question of the defendant’s damages.”

¶26The court, however, did, in answer to a suggestion-of counsel for defendant, that the latter would have a right to damages for-the withdrawal of the contract by plaintiff, proceed to make some remarks on that subject to which defendant excepts, and which he now assigns for. error.

¶27We do not see any thing in these remarks to complain of, except that they were irrelevant to any issue in the case. There was no plea or cross-demand under which those damages could have been passed upon by the jury. As they in nowise prejudiced defendant in-the present action, we are not called on to consider further their soundness as matter of law.

¶284. The court was asked to instruct the jury “that verbal admissions, while, if deliberately made and precisely identified, they frequently furnish satisfactory evidence, are to be received with great caution; and the attention of the jury should be directed, in passing upon alleged verbal admissions, to whether *429the witnesses testifying thereto distinctly understood the party charged in what he said, and whether-they have or have not, intentionally or unintentionally, failed to express what was actually said.” But the court "refused said instruction.

¶29This is the ground of the last assignment of error..

¶30There is nothing in the testimony, as we find it in the bill of exceptions, to which such a charge could apply. There are no admissions, properly so called, of defendant relied on in the case. The testimony in regard to the renewal of the contract after plaintiff’s letter to defendant, that he would receive no more stone from him, is not an admission: it is a conversation betwéen plaintiff and defendant, in which the contract is renewed or the abandonment waived. It- is explicitly stated by plaintiff that defendant agreed to recommence the delivery of stone and complete the contract. Whatever else this may be, it is no admission. This word, in the sense of the quotation from Greenleaf, asked by counsel as a charge, means an admission by a party of. some existing fact or circumstance which • tells against him in the trial, and does not relate to the terms in which a substantive verbal contract is made by the parties.-

¶31Besides, it is apparent that the attention of the jury- was directed- by the court to all the matters essential to their understanding the case; and we do not admit that.a court is bound to give to the jury, at the instance of counsel, every philosophical remark found in text-books of the law, however-wise or true they may be in the abstract, or however high the reputation of the author.

¶32We find no error in the record, and the judgment of the Circuit Court is

¶33Affirmed.

/96/us/424 · .json · Public domain