Design-build, progressive design-build, and general contractor/construction manager procedures—Public works projects.

Applied in 2 court decisions — leading case STATE EX REL.(CAT) v. Murphy (2004)

Most recently applied in STATE EX REL.(CAT) v. Murphy (April 2004)

2025 c 231 s 4; 2015 3rd sp.s. c 18 s 2; 2006 c 37 s 1; 2001 c 226 s 3.

(1) The department of transportation is authorized to use the design-build procedure, progressive design-build procedure, and any general contractor/construction manager procedure for public works projects.

(2) For the first three general contractor/construction manager projects that the department delivers, the department shall pursue approval in accordance with RCW 39.10.280. After three such approvals have been granted, the department is not subject to the approval requirements of RCW 39.10.280.

Official source: Washington State Legislature. Reproduced from public-domain Washington statutes; confirm against the official source for the current text. Not legal advice.